Ontario amends property tax treatment of renewable energy installation

James Klein and Annie Pyke -

On January 4, 2012, Ontario amended O. Reg. 282/98 under the Assessment Act to provide new rules with respect to the assessment of property taxes on renewable energy installations. These amendments apply to facilities that generate electricity using solar energy, wind energy or anaerobic digestion of organic matter. The amendments differentiate between rooftop and ground solar installations, as well as between entities whose primary business is the generation, transmission or distribution of electricity (corporate power producers) and persons who are not ordinarily in the business of electricity generation (ancillary producers).

For rooftop solar installations the amendments provide that the assessment and tax classification of property will not change due to the addition of a renewable energy installation on the rooftop of a building. For ground-mounted installations, the property tax treatment will depend upon the size and location of the facility as well as who is conducting the generation.  Corporate power producers will be taxed at the industrial rate, regardless of the size of the facility. With respect to ancillary producers, no changes were made with respect to ancillary producers up to 10 kW. Ancillary producers of greater than 10 kW of solar or wind energy will be taxed at the surrounding land use rate for up to 500 kW and then at the industrial rate for the proportion over 500 kW. On-farm anaerobic digesters over 10 kW, which are operated by farmers, will be taxed at the surrounding land use rate regardless of size. These amendments took effect as of January 1, 2011.

Transmission line for renewable energy park approved

Patrick Duffy and Daniel Suss -

Grand Renewable Wind LP (GRW) has received approval from the Ontario Energy Board to construct a new transmission line and associated facilities for the Grand Renewable Energy Park (GREP) located in Haldimand County.  The Board’s approval is subject to GRW obtaining all other necessary approvals, including its Renewable Energy Approval for the GREP, and complying with certain mitigation measures.

GRW’s application was one of first leave to construct applications since the enactment of the Green Energy and Green Economy Act, 2009 and it raised novel issues that the Board has not considered before. Of particular interest in this case was a request from Haldimand County Hydro Incorporated (HCHI) for access to GRW’s transmission facilities so that HCHI could connect a new transformer station for its distribution system. GRW denied that it had an obligation to provide HCHI with access to its transmission facility.

The dispute centred on whether GRW, a partnership of Samsung and Pattern, should be treated like a typical transmitter, which would carry with it a requirement to be licenced and an obligation to provide access.  Generally, transmission lines operated by generators are exempt from these obligations provided the line carries the generator’s energy.  The unique twist in this case is that the transmission line will not just carry energy from GRW’s wind farm, but also from a solar facility that will operated by a different entity as part of GREP.

GRW argued that it was exempt from the requirement to hold a transmitter’s licence because it would be generator and would transmit power from the solar project at cost. Board staff and other intervenors disagreed with this argument. In its decision, the Board acknowledged the issue was important, but determined that it was not necessary to decide the issue as part of a leave to construct application.

It is not clear from the decision how the Board intends to resolve this issue.  If HCHI intends to pursue the issue, it could make a specific application for access to GRW’s transmission facilities. Alternatively, the Board could convene a generic proceeding under its Transmission System Code to deal with the matter more generally. 

Ontario Government Announces FIT Review

On October 31, 2011, the Ontario Government announced its first review of the FIT program. The review, which will be led by Deputy Minister Fareed Amin, aims to tackle issues including price reduction, long-term sustainability, job creation, new technologies and local consultation.

Ontarians are invited to participate in the review during the consultation period from October 31, 2011 to December 14, 2011. The OPA will also be holding a webinar tomorrow, November 2, 2011 at 10 a.m. in order to provide additional information.

Any FIT contracts awarded subsequent to today’s announcement will be subject to the new rules and pricing schedule that result from the review. Existing contracts will not be affected. The OPA is offering to refund application fees for those who wish to withdraw their application as a result of today’s announcement.

Ontario Court ruling an important precedent for wind farm developers

Patrick Duffy -
 
Wind farm developers in Ontario are being threatened with litigation from neighbouring residents who claim property values are suffering because of the perceived health concerns associated with wind turbines.  These claims were recently the subject of an investigation undertaken by the CBC that reported homes near wind farms were selling for less and taking longer to sell than other homes.  The issue has also been raised before the province's Assessment Review Board by property owners seeking to lower their property tax assessments.
 
A recent ruling from the Ontario Court of Appeal in Ellen Smith v. Inco Limited will provide the province's wind developers with  stronger hand in fighting back against such claims.  The claimants in the Inco case alleged that their property values were reduced by nickel contamination that originated from Inco’s refinery in Port Colborne.  They succeeded at trial and Inco was held liable for the tort of nuisance and under strict liability imposed by the rule in Rylands v. Fletcher.   The ruling was notable as the refinery had adhered to the applicable environmental regulations during its operation and the level of nickel contamination did not present a threat to human health or otherwise impact the complainants' ability to use and enjoy their property.  Nonetheless, the trial judge held Inco liable for the loss of property value because the contamination led to a negative public perception about the contaminated land.

The Court of Appeal overturned the trial decision on October 7, 2011. On the issue of nuisance, the appeal judges ruled that an allegation of reduced property values cannot succeed in the absence of "actionable, substantial, physical damage" to the property or substantial interference with a claimant's use or enjoyment of his or her land. Neither of those were present in the Inco case. The court specifically noted that public concerns about potential health effects are insufficient to establish liability unless the alleged contamination "caused actual harm to the health of the claimants or at least posed some realistic risk of actual harm to their health and wellbeing." The court was critical of the trial judge's approach to nuisance because it would have allowed claims to succeed based on "unfounded public concerns" and "junk science" even where a defendant proved the contamination did not pose a risk to human health. The trial judge's finding of liability under the rule in Rylands v. Fletcher was also set aside because Inco had operated the facility in a manner that did not create "extraordinary or unusual" risks beyond those incidental to virtually any industrial operation.

The Court of Appeal's decision is good news for wind developers confronted with loss of property value claims from nearby residents. As a result of Inco, a claimant cannot rely upon vague allegations of reduced property values; rather they will be required to demonstrate the reduction arises either from actual physical damage to the property or a substantial interference with their ability to use and enjoy the property.

The Court of Appeal's decision may not be the final word on the matter as the plaintiff in Inco has the right to seek leave to appeal the decision to the Supreme Court of Canada.

Ministry of Finance proposes property tax amendments for renewables

The Ministry of Finance is proposing amendments to Ontario Regulation 282/98 that will alter the property tax treatment of certain renewable energy installations for the 2011 tax year. A summary of the proposed changes can be found in the table below.

The amendments will only apply to ground-mounted solar, wind and anaerobic digestion facilities where generation is ancillary to the main activity on the property. The aim is to reduce any disincentive property taxes may pose to individuals who are not ordinarily in the business of generation.

Consistent with current treatment, land, buildings and structures used for ground-mounted solar and wind facilities operated by entities whose primary business is generation will continue to be taxed at the industrial rate. Additionally, there is no change to the fixed rate applicable to ground-mounted wind turbines over 10kW: they will continue to be assessed at $40,000 per MW of installed capacity. As such, the amendments are meant to build upon the existing regulatory framework and establish greater clarity by creating additional categories for assessment based on the size and location of generation.

The Ministry is currently seeking public comment until August 29, 2011. Individuals wishing to do so may submit comments directly from the Regulatory Registry web site by clicking here:

 

Small
(up to 10 kW)

Medium
(over 10 kW up to 500 kW)

Large
(over 500 kW)

Rooftop


No new assessment or taxes.

Ground – Ancillary Use:

Generation is not performed by corporate power producer and is secondary to main activity on property

 


Land, buildings and structures used for electricity generation are taxed at the rate of the surrounding land use.

This treatment also applies to large (over 500 kW) on-farm anaerobic digesters that are operated by farmers.


Land, buildings and structures used for electricity generation are taxed at the rate of the surrounding land use for the proportion of assessment up to 500 kW, and taxed at the industrial rate for the proportion over 500 kW.

Ground – Professional Generation:

Generation is conducted by corporate power producer




Land, buildings and structures used for electricity generation are taxed at industrial rate.

Ontario amends Samsung agreement

The Ontario government has announced the amendment of its green energy investment agreement with Samsung C&T Corporation and the Korea Electric Power Corporation (Samsung). The $7 billion dollar agreement is for the development of 2,500 megawatts worth of renewable energy generation (wind and solar) in addition to building four clean-technology manufacturing plants.

In February 2011, Ontario’s Feed-In Tariff contract-holders were granted a one year extension to their commercial operation date. In exchange for a similar extension, Samsung has agreed to a number of significant revisions to its original agreement signed in January 2010.

For instance, economic development payments to Samsung that were previously projected at $437 million have been reduced by 75% to $100 million. These payments will only become due upon commercial operation of manufacturing plants and renewable facilities. Additionally, the payments will be contingent on meeting job commitments made in the agreement.    

Moreover, the revisions will have the four clean-technology manufacturing plants operating one year earlier than expected. Plants in Windsor, Tillsonburg and Toronto are expected to begin operation shortly.

OPA waives pre-NTP termination rights for FIT contracts

On August 2, 2011, the Ministry of Energy directed the OPA to allow Suppliers under Ontario’s Feed-In Tariff (FIT) program to obtain a waiver of the OPA’s termination rights contemplated in section 2.4(a) of the FIT Contract.

Obtaining a waiver of this termination right is meant to expedite issuance of a Notice to Proceed (NTP) by reducing contractual termination risk and allowing Suppliers to procure financing for equipment orders. 

Section 2.4(a) permits either the OPA or the Supplier to unilaterally terminate the FIT Contract at any time before the OPA issues a NTP and the Supplier has paid the Incremental NTP Security.

Different submissions and deadlines will apply to Capacity Allocation Required (CAR) Suppliers and Capacity Allocation Exempt (CAE) Suppliers.

CAR Suppliers requesting the OPA waive section 2.4(a) are required to submit the following documents: (i) the waiver and a Domestic Content (DC) Plan by October 14, 2011; and (ii) evidence of one or more agreements for the purchase of Generating Equipment demonstrating the Supplier will meet or exceed the Minimum Required Domestic Content Level, by November 30, 2011. The DC plan will be reviewed for completeness and substantiation by December 31, 2011.   

CAE Suppliers are required to submit the waiver and DC plan by December 31, 2011.

In each case, OPA termination rights will be automatically reinstated if these deadlines are not met. Additionally, all Suppliers must continue to provide the OPA with a NTP Request and satisfy necessary NTP pre-requisites including a Renewable Energy Approval, Financing Plan, DC plan, and Impact Assessments.

The waiver and associated schedules are expected to be available shortly.

The OPA will be hosting a webinar to discuss the waiver process and answer questions on August 9, 2011 at 2:00 p.m. (ET). In the meantime, the OPA has requested Suppliers not contact their offices until after the webinar has been held. To participate in the webinar, you may log into the web link below. In order to ask a question, you will have to contact the toll-free number found below.

Toll Free Phone Number: 1 (866) 212 9078

Web link: http://www.snwebcastcenter.com/event/?event_id=2025

Highly anticipated ERT decision issued for Erickson v Director, Ministry of Environment

On July 18, 2011, The Environmental Review Tribunal (ERT) issued its highly anticipated decision in Erickson v Director, Ministry of Environment. The ERT found that the applicant in this case did not meet the burden of showing that the project will, more likely than not, cause serious harm to human health. However, the decision is by no means a conclusive endorsement of the safety of wind turbines.

The high-profile appeal alleged that Suncor’s Kent Breeze Wind Project (Project) posed negative human health risks as approved by the Minister of the Environment (MOE) under Ontario Regulation 359/09 (REA). Over 17 days between February 1 and May 26, 2011 the ERT heard testimony of leading experts from around the world on the potential health effects of wind turbines.

The Project in question is a 20 MW Class 4 Wind Facility consisting of eight wind turbine generators in the Chatham-Kent region. On November 10, 2010, the MOE issued an REA to the Project under section 47.5 of the Environmental Protection Act (EPA). Shortly afterwards, that decision was appealed by Katie Erickson and the Chatham-Kent Wind Action Group. The appeal alleged that the Project posed negative human health risks including unsafe exposure to low frequency noise and shadow flicker. Additionally, the applicants raised concerns associated with the adverse visual impact of turbines, the negative risks of ice-throw and turbine failure.

In a detailed 223-page decision the ERT found that the applicants had failed to demonstrate that the Project will, more likely than not, cause serious harm to human health. However, the ERT explicitly acknowledged the risks and uncertainties associated with wind turbines and noted that the science behind the health effects of wind farms is in its infancy and is neither exhaustive nor conclusive. The ERT observed that continued research will resolve some of these concerns.

The ERT also noted that the question is not simply whether wind farms will cause serious harm to people, but is a question of degree: “what protections, such as permissible noise levels or setback distances, are appropriate to protect human health”? In this regard, the decision appears to find the REA regulations sufficient in the context of Kent Breeze Project. However, the ERT refused to confirm the adequacy of the REA process more generally. As such, while Erickson may at first blush appear as a victory for the renewable energy developers, the debate may be far from over.

The applicants will have until August 18, 2011 to appeal the ERT decision to the Divisional Court on a question of law.

U.S. wind player launches NAFTA challenge against Ontario's Green Energy Act and Feed-in Tariff Program

Dallas-based Mesa Power Group LLC ("Mesa") has filed a Notice of Intent with the Canadian federal government indicating that it will challenge Ontario's Green Energy Act ("GEA") and Feed-in Tariff Program ("FITP") for alleged violations of the North American Free Trade Agreement ("NAFTA").

Mesa had two proposed wind projects in the Bruce transmission region of Western Ontario which were not recipients of FITP Power Purchase Agreements ("PPA") with the Ontario Power Authority ("OPA").

In its Notice of Intent filing, Mesa claimed that changes made by OPA to the rules for awarding PPAs in the Bruce transmission region violated Article 1105 of NAFTA with respect to non-discriminatory treatment of investors of another NAFTA signatory.  Mesa also claimed, among other things, that the GEA contains "buy local" performance requirements that contravene Article 1106 of NAFTA.

Mesa stated that it expects to file a formal NAFTA Notice of Arbitration some time after October 3, 2011.

IESO approves new data obligations for renewable facilities

Andrew Sullivan -

Beginning November 1, 2011, many wind and solar PV generators will be required to submit real-time meteorological and output data to the IESO.

The market rule amendment is part of IESO plans for renewable integration. As part of this integration, the IESO is seeking to implement centralized forecasting. Instead of providing energy forecasts, renewable facilities will be required to submit real-time, site specific data (“dynamic data”) to the IESO that will be used to produce variable generation forecasts provided by a third-party.

The requirements will apply to all wind and solar facilities connected to the IESO-controlled grid in addition to embedded non-market participants with an installed capacity over 5MW.

Starting November 1, 2011 these facilities will be required to submit both site-specific data in addition to their own forecasts. Once the IESO has implemented its central forecasting approach, renewable generators will no longer be required to submit their own forecasts. However, there is no indication from the IESO of an exact date centralized forecasting will be implemented.          

Of particular note, the market rule amendment specifies reporting standards. 

In addition to dynamic data, both wind and solar facilities will be required to provide information concerning the physical layout and details of the facility (“static data”) at the time of connection assessment and/or registration. A summary of these collection requirements are found below.

Wind  

For wind facilities, the following static and dynamic data will be required:

 Static Data  Description
 Turbine Hub location  Turbine Hub location (latitude and longitude), height, and elevation from sea level.
 Meteorological (MET) Tower location  Physical location (latitude and longitude), height, and elevation from sea level.
 Type of turbine  Whether the turbine is a horizontal or vertical axis type.
 Manufacturer’s power curve  Power curve maps containing expected output for a turbine at varying wind speeds.
 Cut in speed  The lowest wind speed (metres per second [m/s]) at which the turbine will generate power.
 Cut out temperature  The maximum and minimum ambient temperature (in °C) at which the wind turbine will be shut down to prevent physical damage.

 

Dynamic Data Unit of Measure Height of Measurement Precision (to the nearest…)
Wind Speed Metres per Second (m/s) Hub height 0.1 m/s
Wind Direction   Degrees from True North Hub height 1 degree
Ambient Air Temperature Degrees Celsius (°C) Hub height or 2m 0.1 °C
Barometric Pressure Hectopascals (HPa) Hub height or 2m 60 Pa
Relative Humidity Percentage (%) Hub height or 2m 1.0%
MW outputs (per facility) Megawatt (MW) N/A 0.1 MW
Available Megawatts Megawatt (MW) N/A 0.1 MW

 

Additionally, the IESO had mandated collection standards for dynamic data listed above. At minimum, each facility will be required to provide this data from nacelle mounted data collection points. Every turbine is required to be within 5km from the nearest data collection point. Furthermore, each facility over 10MW will be required to provide data from at least one standalone meteorological tower. The number of towers required will correspond to the facility size (MW). Towers will be required located on the prevailing upstream side of the wind facility in areas that have representative microclimates and winds at hub height. Data is to be reported to the IESO in real-time every 30 seconds.

Solar

For solar facilities, the following static and dynamic data will be required:

Static Data Description
Solar facility location (latitude and longitude) Physical location (GPS coordinates) of each solar array.
Meteorological data collection device location and elevation (latitude and longitude) Physical location (GPS coordinates) of each met data collection device, its elevation and height of measurement.
Elevation and orientation
angles of arrays
Height from ground level and angle of each solar array, Tilt (angle with horizontal plane) and Azimuth (angle in North-East-South West Plane)
Power Rating Rated Power at standard test conditions.
Generation capacity of the generating facility and each generating unit The name plate capacity of the entire facility with a breakdown for each array within the system. (DC and AC Power at standard test conditions for arrays and power of inverters.)
Temperature Coefficient Temperature coefficient of the module power at the maximum power point,
Type of Mounting Ground Mount, Rooftop, Rack Mount, Fixed or Solar Tracking etc
Module Type Crystalline, Thin-Film, Concentrated PV (CPV) etc

 

Measurment Type Definition Unit of Measure Data Required for Measurment Precision
Plane-of-Array Irradiance (POA) Measurements perpendicular to the solar receiver Watts/ Square Meter Crystalline, Thin-Film, CPV +/- 25W/m2
Global Horizontal Irradiance (GHI) The solar resource available to a flat-plate collector oriented horizontal to the earth’s surface Watts/ Square Meter Crystalline, Thin-Film, CPV +/- 25W/m2
Global Diffused (GDIFF) Solar radiation that has been scattered out of the direct beam Watts/ Square Meter CPV +/- 25W/m2
Direct Irradiance (DNI) The amount of solar radiation received per unit area by a surface that is always held perpendicular (or normal) to the rays that come in a straight line from the direction of the sun at its current position in the sky. Watts/ Square Meter CPV +/- 25W/m2
Ambient temperature at the average height of the array Ambient temperature at the array average height Degrees Celsius (°C) Crystalline, Thin-Film, CPV   1 °C
Back of Module Temperature Average temperature at the back of module Degrees Celsius (°C) Crystalline, Thin-Film, CPV 1 °C
Barometric pressure Barometric Pressure Pascals (Pa) Crystalline, Thin-Film, CPV 60 Pa
Wind speed and direction at the average array height Anemometer, wind vane or wind mast readings Meters/Second (m/s) Crystalline, Thin-Film, CPV 1 m/s
MW output (per facility) Current Megawatt (MW) output for the facility  Megawatt (MW) Megawatt (MW)  Crystalline, Thin-Film, CPV 0.1 MW
Available Megawatts What the facility can produce after deducting outages Megawatt (MW) Crystalline, Thin-Film, CPV 0.1 MW

 

Like wind, solar will be subject to data collection standards. At minimum, each facility will be required to have two meteorological data collection points. All solar arrays in that facility are required to be within 12km of a collection point. Data must be provided to the IESO every 30 seconds.

For both wind and solar PV, there is no requirement that the data collection devices be owned by the same owner of the facility.

Stakeholder Engagement

These new obligations are part of a larger IESO plan to accommodate the phase-out of coal and increased contribution of wind and solar. These developments will significantly impact Ontario’s electric grid. Declining demand and variability associated with renewable sources could result in a surplus of baseload generation. Furthermore, the IESO is facing a reduced flexibility to deal with the variability of supply due to increased regulatory constraints and limited ramping ability of gas facilities (compared to coal).

In an attempt to accommodate this variability, the IESO will implement changes to three major areas: forecasting, visibility and dispatch. The IESO is currently undertaking stakeholder engagement initiative (SE-91) in an effort to include stakeholders, such as developers and distributers, in the talks surrounding these changes.

Currently, eleven design principles have been approved relating to the three areas of change. This amendment is based upon SE-91 Renewable Integration Final Design Principles - Principles 1, 4 and 5. 

The Ontario Power Authority (OPA) is watching SE-91 closely. It has committed to working with supplies on OPA contract issues that may result from these IESO rule amendments (RESOP, RESIⅈ RESIII, FIT, HCI).

In any event, the IESO will continue consulting with stakeholders in renewable integration. Currently, two working groups for SE-91 exist: the Dispatch Technical Working Group and the Visibility Technical Working Group. This fall, the IESO intends to form a dispatch merit order working group that will comment on the order of curtailment in the event of baseload surplus.

For more information on SE-91 or to participate in the next meeting, email stakeholder.engagement@ieso.ca.

Bruce to Milton Line FIT contracts announced

Yesterday the Ontario Power Authority offered Feed-in Tariff contracts to 19 large scale on-shore wind projects and 6 ground-mount solar projects, totalling nearly 1,046 MW of new renewable energy projects. 750 MW of wind-based contracts were offered in the Bruce Area and the remaining 296 MW were offered in the West of London Area, 27.5 MW for ground-mount solar and 268.4 MW for on-shore wind.

The biggest winner of the contract offers is Boulevard Associates Canada, Inc., with 335 MW offered in the Bruce Area. International Power Canada, Inc. received offers for 198 MW in the West of London Area.

The Bruce to Milton Transmission Project is one of the largest transmission projects in Ontario in the past 20 years and will see the construction of more than 180 km of 500 kV transmission line between the Bruce Power facility in Kincardine to Hydro One’s Milton Switching Station. Although the earliest in-service date for the new line is the end of 2012, many renewable energy project developers have been eagerly awaiting any announcements on the implications of this additional transmission capacity on the availability of FIT contracts. The announcement follows the OPA’s June 3 announcement in which eligible proponents were granted five days to change the connection points of their projects in order to qualify for over 1,000 MW of capacity along the Bruce to Milton line. Contract offers were to be based on the results of DAT/TAT testing from the new connection points of all eligible projects, taken together with the priority ranking of projects in the Bruce and West of London transmission areas established in previous testing.

These contract offers are expected to be some of the last for large scale renewable energy projects prior to October’s provincial election.

Further information is available from the OPA’s FIT website: http://fit.powerauthority.on.ca/

Anti-wind turbine crusader's case comes to an end

Patrick Duffy

Ian Hanna, an Ontario anti-wind crusader, has been denied permission to appeal an earlier court decision that dismissed his judicial review application. 

Hanna’s application challenged Ontario Regulation 359/09 that governs renewable energy approvals in Ontario. The Regulation requires a 550 meter distance between wind turbines and noise receptors such as residences.

Hanna argued that there was no scientific basis for the 550 setback. He challenged the regulation on the basis that the Minister of Energy had not followed the necessary process required by Environmental Bill of Rights (EBR). Section 11 of the EBR requires the Minister to consider the Statement of Environmental Values (SEV) when making decisions that might significantly effect the environment. In turn, the SEV requires the Ministry to “use a precautionary, science-based approach in its decision-making”. Hanna argued the Ministry had failed to meet that requirement when it determined the setback distance.

Hanna’s application went before the Ontario Divisional Court and was dismissed in March 2011. The court was satisfied that the Minister complied with the process required by the EBR and SEV. In support of this, the court cited public consultation and a science-based ministerial review using World Health Organization reports and acoustic engineering experts. 

Hanna vowed to fight on and sought leave to appeal the decision to the Ontario Court of Appeal, but on June 20 the court denied his application.

InterSolar Europe in Munich abuzz with German government announcing nuclear exit by 2022

Eric Bremermann -

The international renewable energy and general electricity generation community that gathered at Intersolar Europe from June 8 to 10 was abuzz digesting the news of the German parliament releasing its plan to have the country’s electricity generation fully withdraw from nuclear energy by 2022. I attended the Intersolar Europe and observed optimism among solar industry participants that Germany’s nuclear exit will bring new opportunities in the German solar market. That country’s solar market had begun to lag in recent times due to solar feed-in-tariffs being curtailed. However, as Germany today only relies on roughly twenty percent nuclear power, the German government’s announcement was primarily seen as producing significant new opportunities for development of substitute base load capacity, which is thought will have to come from utility scale offshore wind parks, as well as natural gas fired plants

OPA offers 40 new FIT contracts

This morning, the Ontario Power Authority announced contract offers for 40 large scale renewable energy projects under the Feed-In Tariff Program, representing over 872 megawatts of renewable power.

Although only four of the contracts offered are for on-shore wind projects, on-shore wind is the energy source for over 70% of the capacity offered.  Thirty-five solar projects (33 groundmount and two 500kW rooftop) represent over 29% of the capacity. A single water-power project of 500 kW makes up the balance. By region, 49% of the capacity is in the central region, 22% in the east and 28% in Niagara.

The announcement reflects the long anticipated results of the OPA’s transmission and distribution availability tests (so called TAT and DAT). Contract offers for smaller capacity allocation exempt(or CAE) projects are expected to follow over the coming weeks.

The list of contracts offered is available from the OPA FIT website.

Ontario halts offshore wind projects

The Ontario government announced on Friday that the province will not proceed with any proposed offshore wind projects until further scientific research is completed. The press release circulated mid-Friday afternoon noted that no renewable energy approvals for offshore projects have been issued to date, no new applications for offshore wind projects under the OPA’s FIT program will be accepted and current applications for such projects will be suspended.

To date only one off-shore wind project has been granted a FIT contract, although without the necessary renewable energy approval from the Ministry of Environment, the project will be unable to meet its obligations under such contract. Three additional off-shore wind projects are listed as awaiting connection tests under the FIT program; today’s announcement will see such applications suspended.

This announcement comes as the Ontario government is attempting to balance its commitment to renewable energy in the face of increasing public criticism of wind energy projects related to health and safety and environmental concerns.

Ontario amends Renewable Energy Approvals regulation

The Ontario government has published amendments to the Renewable Energy Approvals Regulation (O. Reg. 359/09) that will take effect on January 1, 2011.  We reported on an earlier version of the proposed amendment in an October blog posting.

The most significant changes in the amended regulation concern noise receptors and setback requirements for wind faculties. As a result of the amendments, the term “overnight accommodation” in the definition of noise receptors will be replaced with a definition of “dwelling” based on the definition in the Building Code. The definition of “dwelling” was also modified by replacing the words “intended to be used” with “capable of being used”.These changes appear to set a higher threshold for what structures qualify as a dwelling.

The well-publicized 550 metre wind turbine setback prohibitions in the original regulation required proponents to consider all noise receptors at the time of construction and did not contemplate that the surrounding conditions could change between the time of approval and time of construction. This created uncertainty for proponents as they could not necessarily rely upon an approval as compliance with the setback requirement at the time of construction. This concern has been addressed by these amendments, which only require proponents to consider noise impacts to surrounding noise receptors that existed as of the date the location of the facility was made public.To allow the MOE to assess the cumulative impacts of the facility, the amended regulation will also require proponents to consider all existing and publicly known projects in the surrounding area when complying with the noise setback requirements and determining a site plan.

Other changes under the amendments affect the public notifications required for renewable energy projects and revise the requirements for municipal consultations.

A summary of the changes has been posted on the environmental registry.

Canadian tax considerations for windpower and solar power projects

John Lorito

The following is a brief summary of the main Canadian federal income tax considerations applicable to windpower and solar power projects in Canada and, in particular, the accelerated capital cost allowance rates for qualifying depreciable property and the Canadian renewable conservation expense regime. 

Accelerated Capital Cost Allowance Rate

“Capital cost allowance” (CCA) is essentially depreciation for Canadian federal income tax purposes. CCA deductions are discretionary and are taken on a declining balance, class-by-class basis. For example, if the capital cost of depreciable property of a particular class is $100 and the CCA rate for the class is 30%, CCA to a maximum of $30 may be claimed in respect of the property in the first year (subject to the half-year rule discussed below). If $20 of CCA is claimed, this amount is deducted from the capital cost to arrive at the “undepreciated capital cost” (UCC) and the 30% rate is applied to this amount to determine the maximum deduction in the following year (in this example, $24). The cost of newly acquired property of the same class is added to the UCC and proceeds from the sale of property in the class (up to the original cost of the property) is deducted from the UCC. If the UCC is negative at the end of a year, the negative amount (known as recapture) is included in computing income in that year.

CCA classes 43.1 and 43.2 of the regulations (the Regulations) under the Income Tax Act (the Act) provide enhanced CCA rates for various renewable asset properties. Certain assets of a qualifying wind energy conversion system or photovoltaic system that are included in class 43.1 will be entitled to an accelerated CCA rate of 30% per year. Such assets that are acquired after February 22, 2005 and before 2020 and that would otherwise be included in Class 43.1 are included in class 43.2, which has a CCA rate of 50%. 

Subject to certain exceptions, Class 43.1 includes

  1. a fixed location device that is a wind energy conversion system that

    1. is used by the taxpayer primarily for the purpose of generating electrical energy, and
    2. consists of a wind-driven turbine, electrical generating equipment and related equipment, including

      1. control, conditioning and battery storage equipment,
      2. support structures,
      3. a powerhouse complete with other ancillary equipment,
      4. transmission equipment; and
         
  2. fixed location photovoltaic equipment that is used for the purpose of generating electrical energy from solar energy consisting of solar cells or modules and related equipment including inverters, control, conditioning and battery storage equipment, support structures and transmission equipment.

There are certain limitations that apply in determining the amount of CCA that may be deducted in any given taxation year. By virtue of the “available for use rules” in the Act, CCA for a Class 43.1 or 43.2 property that has been acquired and which is not considered available for use at the end of a taxation year may be restricted until such time as the property is available for use. In addition, property that becomes available for use in the year is subject to the “half-year” rule found in the Regulations, whereby only 50% of the normal CCA deduction is permitted in the year an asset becomes available for use. Finally, CCA is prorated in circumstances in which the taxpayer’s taxation year is less than 365 days.

Property included in Class 43.1 or 43.2 may be “specified energy property” in which case, the CCA that may be deducted by a taxpayer in respect of such property is limited to the taxpayer’s income from the business of selling the product of the property. This limitation does not apply to a corporation whose principal business is manufacturing or processing, mining operations or the sale, distribution or production of electricity, natural gas, oil, steam, heat or any other form of energy or potential energy, or to a partnership each member of which is such a corporation.

Canadian Renewable and Conservation Expense (“CRCE”)

Certain expenses incurred by a taxpayer in the pre-production development phase of renewable energy and energy conservation projects, for which it is reasonable to expect that at least 50% of the capital cost of the depreciable property to be used in the project would qualify for inclusion in Class 43.1 or 43.2, may qualify as CRCE if, among other things, they are not:

  1. payable to a person or partnership with whom the taxpayer is not dealing at arm's length (such as a parent, subsidiary or sister company), or
  2. specifically excluded from CRCE under subsection 1219(2) of the Regulations (see below).

Where expenses qualify as CRCE, they may be deducted entirely in computing Canadian taxable income in the year they are incurred or carried forward indefinitely and deducted in later years.

Examples of the types of expenses that are typically eligible for CRCE include expenses incurred by a taxpayer:

  1. for the purpose of making a service connection to the project for the transmission of electricity to a purchaser of the electricity to the extent that the expense was not incurred to acquire property;
  2. to determine the extent, location and quality of energy resources;
  3. for clearing land to the extent necessary to complete the project;
  4. for the construction of a temporary access road to the project site; and
  5. for a “test wind turbine” that is part of a wind farm project of the taxpayer. 

Examples of the types of expenses that are not eligible for CRCE include:

  1. amounts that would otherwise be included in the capital cost of depreciable property, including all costs directly associated with the acquisition and installation of the property, except those described in i) to v) above as qualifying as CRCE;
  2. financing and interest charges;
  3. administration and management expenses;
  4. amounts paid to a non-resident person or a partnership any of the members of which is not a resident of Canada; and
  5. costs related to the acquisition or use of land, as well as the grading and levelling of land, except those described in i) to v) above as qualifying as CRCE.
  6. The determination of whether a particular expense incurred by a taxpayer will qualify for inclusion in CRCE must be made based upon a review of all of the facts relevant to a particular situation. 

Special Rules Applicable to Limited Partnerships

Where windpower or solar power projects are carried on through limited partnerships, additional considerations arise. A partnership is not a taxpayer for Canadian tax purposes. Rather, a partnership computes its income (or loss) as a separate person resident in Canada and then allocates the income or loss to its partners. If a taxpayer is a member of a partnership at any time in a particular taxation year, it will include in computing its income its share of the income or loss of the partnership for any fiscal period of the partnership ending in, or at the same time as, such taxation year.

There are two exceptions to this general scheme that are relevant to limited partnerships that carry on windpower or solar power projects.  First, any CRCE incurred by a partnership is not deductible in computing income or loss that is allocated to its partners but, instead, each partner deducts directly its share of any CRCE incurred by the partnership. In addition, in the case of a limited partner, the deduction of any loss of the partnership or CRCE incurred by the partnership is restricted to the limited partner’s “at-risk amount”. Generally, a limited partner’s at-risk amount in respect of its interest in the partnership at any time is equal to the cost of the limited partner’s interest in the partnership plus any income allocated to the partner for fiscal periods ending prior to that time less the sum of any losses of the partnership allocated to the partner for fiscal periods ending prior to that time and any distributions received by the partner from the partnership before that time. To the extent that a limited partner’s share of the loss from the partnership or CRCE incurred by the partnership exceeds the partner’s at-risk amount, such loss or CRCE may be deducted in a subsequent year to the extent that the amount of the loss or CRCE does not exceed the partner’s at-risk amount in that subsequent year.

FIT Program Update: Updated Timeline

On October 18, 2010, the OPA released an updated timeline for the FIT Program indicating that Transmission Availability Tests and Distribution Availability Tests would commence on October 18, 2010 for non-capacity exempt project applications submitted between December 1, 2009 and June 4, 2010.  The results of such tests are intended to be released in late November 2010.  The existing timeline which was released on June 1, 2010 contemplated that the results of the tests would be released in early July 2010. 
 
Non-capacity allocation exempt applications submitted after June 4, 2010 will be reviewed following the completion of the upcoming Economic Connection Test.  The OPA intends to post an update on the timing of the Economic Connection Test.
 
Applications for capacity allocation exempt projects are reviewed and offered contracts on an ongoing basis.  Contract offers for applications submitted after June 4, 2010 are expected to begin in late October 2010.

Ontario Ministry of Environment posts draft amendments to the Renewable Energy Approvals Regulation

The Ontario Ministry of the Environment has posted a draft amend to the Renewable Energy Approvals Regulation (O. Reg. 359/09) to provide clarity with respect to the regulatory requirements that proposed renewable energy projects must satisfy.  The proposal notice and a draft of the regulation can viewed on the Environmental Registry.
 
Perhaps the most notable amendments include changes to the definition of noise receptors and clarification of the noise receptor setback prohibitions for wind facilities. Uncertainty over the proper interpretation of the current requirements has been a concern of the developers of these facilities.   Other changes of note include stronger requirements for mandatory consultations with the public, Aboriginal communities, municipalities and the Niagara Escarpment Commission, and changes to the assessment of protected properties, protected properties, archaeological and heritage resources, and natural heritage assessment and water assessment.

Instructions on FIT NTP

On September 15th, 2010, the Ontario Power Authority released instructions on applying for Notice to Proceed ("NTP") under the Feed-In Tariff Program (the "FIT Program"). The NTP is used to provide confirmation to begin building a project under the FIT Program. The OPA  will issue an NTP when it is reasonably confident that a Project has (i) secured proper financing; (ii) completed all necessary Impact Assessments; (iii) received any applicable environmental and site plan approvals; and (iv) there is sufficient evidence that the Project will be capable of meeting any Domestic Content Level requirements.

Injunction against Saskatchewan windfarm lifted

The Moosomin World-Spectator reports that the Saskatchewan Court of Queen's Bench has now lifted its injunction against construction of a windfarm near Moosomin.

The original injunction was issued ex parte on August 25th and was in place for six days.  After a hearing of the matter on September 1 with all parties represented, the injunction was lifted and construction of the windfarm resumed the following day.  

Costs have reportedly been awarded to the windfarm owner.  Counsel has estimated that the cost of construction delays is approximately $74,000 per day. 

Wind power coming to the New Jersey shore

The state of New Jersey recently passed the Offshore Wind Economic Development Act (the “OWEDA”) that will require New Jersey’s electricity providers to purchase a certain minimum percentage of their total electricity supply from wind operations in the state’s coastal waters.

The New Jersey Board of Public Utilities (the “BPU“) will have the authority to determine the minimum percentage that utilities must purchase from offshore wind, and will issue offshore-wind renewable energy certificates (“OREC”s) to operators. The minimum percentage will be based on the projected total of the ORECs issued during the first twenty years of all the offshore wind projects’ commercial start dates.

If there are insufficient ORECs available in the market to meet the minimum percentage, the utilities will be required to make a “proportional offshore wind-alternative compliant payment.”

The minimum percentage determined by the BPU must support an offshore wind market of at least 1,100 megawatts, which is enough power for 300,000 homes in this state of 8.7 million people. The OWEDA also authorizes the New Jersey Economic Development Authority to provide tax credits of up to $100 million for offshore wind projects.

The BPU is developing the regulations to establish the OREC program, which will be unveiled in early 2011.

Court issues injunction against Saskatchewan windfarm

The Saskatchewan Leader-Post is reporting that a Saskatchewan court has issued an interim injunction temporarily stopping construction of a windfarm near Moosomin.

The $60 million, 25 MW Red Lily windfarm, owned by Algonquin Power and Gaia Energy, was to have come into service late in 2010 or early in 2011.

The project was to have been constructed with minimum setbacks of 550 metres from residences.  Landowners are seeking to have turbines at least 2000 metres from residences.

The interim injunction stops "all construction-related activity".  Further arguments on the injunction application will be heard on September 7. 

OPA posts finalized pricing for ground-mounted solar PV microFIT projects and updates to the FIT Program

Over the last week, the OPA has posted the following amendments and updates to the FIT Program to its website:

  • Price category for ground-mounted solar PV microFIT projects finalized

On August 13, 2010, the OPA announced that it finalized the 64.2 cents per kWh price category for ground-mounted solar PV microFIT projects.  The revised price applies to all microFIT ground-mounted solar applications submitted after 12 p.m. on July 2, 2010.  In addition to changes to the contract price, the OPA has announced that:

(1) commercial aggregators that lease land or rooftops from individuals for multiple renewable energy projects will no longer be able to participate in the microFIT program;

(2) the OPA will be setting up a microFIT advisory panel to provide advice on the evolution of the microFIT program; and

(3) the advisory panel will be charged with making recommendations regarding the appropriate contract provisions that should apply to aggregators (outside the microFIT program).

In addition, the OPA has granted an extension regarding the 2010 domestic content requirements to eligible ground mounted solar PV applicants who applied to the microFIT program before 12 p.m. on July 2, 2010.  Such applicants will be deemed to have met the 2010 domestic content requirements of 40 percent if the project is installed and a connection request has been made by May 31, 2011.  Those applicants which submitted their applications after 12 p.m. on July 2, 2010 will be required to meet 2011 domestic content levels if they are not installed and connected by December 31, 2010. 

A webinar will be hosted on August 18 from 2 p.m. to 4 p.m. to answer questions about these recent developments.  Details on the webinar can be found at the OPA Website

FIT Rules and FIT Price Schedule amended to temporarily disallow applications for 10 KW or less

On August 16, 2010, the OPA announced that the FIT Rules have been revised such that applications for 10 KW or less are not permissible until the microFIT rules and application form have been updated to reflect the new price category and rules for microFIT ground-mounted solar PV projects.  The OPA has indicated new applications under the microFIT program will be accepted beginning on Friday August 20.  The FIT Price Schedule has been updated to reflect the revised price for ground mounted solar PV projects under 10 kW of 64.2 cents/kWh.

  • FIT Prescribed Forms

On August 12, 2010, the OPA updated the Prescribed Forms for the FIT Contract.  The forms can be found at the OPA Website.

Quality Wind Project receives Environmental Assessment Certificate

 Edmonton’s Capital Power announced this week that the British Columbia Environmental Assessment Office had granted an Environmental Assessment Certificate under the B.C. Environmental Assessment Act for its proposed Quality Wind Project, to be located northeast of Tumbler Ridge, B.C.

The $455 million project will consist of 79 wind turbines to be manufactured by Vestas and have a capacity of 142 MW. 

Capital Power expects to commence construction later this year and have the project fully operational by 2012.  An electricity purchase agreement was signed with BC Hydro in April, 2012.

Ontario MNR approves revised onshore windpower policy and procedure

On July 5, 2010 the Ontario Ministry of Natural Resources has approved revisions to its Onshore Windpower Development on Crown Land policy and procedure.

The revisions apply to all onshore Crown land windpower applicants and are part of the MNR’s broader review of Ontario’s Crown land release process applicable to renewable energy projects begun in September 2009.

The aim of the new revisions for onshore wind projects is to eliminate duplication with renewable energy approval processes, provide procedural clarity to applicants currently within the site release process and to align with Ontario’s Green Energy initiative. Revised policy and procedure for offshore windpower projects will follow the government’s broader decision on draft rules regulating off-shore wind turbines proposed by the Ministry of the Environment. The window for new renewable energy applications for Crown land will remain closed until the completion of the phased review.

OPA posts updated FIT contract and rules

The Ontario Power Authority posted Version 1.3.1 of the FIT Contract, FIT Rules, and Standard Definitions on July 2, 2010. A summary of changes of the changes to the FIT Contract, FIT Rules, and Standard Definitions can be found on the OPA's website.  The Ontario Power Authority has also posted a revised Price Schedule to reflect the proposed new pricing for ground-mounted solar PV projects and an updated Program Overview.

Ontario releases draft rules for offshore wind turbines

Alison Forbes

The Ontario Ministry of the Environment  (the “MOE”) released draft rules clarifying the regulation of off-shore wind turbines on June 25, 2010 under the Renewable Energy Approvals regulation under the Environmental Protection Act.

The draft rules, as well as a discussion paper, are available for review and public comment until August 14, 2010 on the Environmental Registry.

The proposal includes a five kilometre “shoreline exclusion zone” for all off-shore wind facilities. Areas within five kilometres from the shoreline of the Great Lakes, other inland lakes and major islands would not be considered for off-shore wind turbines. The exclusion zone is intended to create separation between wind facilities and drinking water intakes and near shore activities and to ensure acceptable noise levels. Additional exclusion zones are proposed to ensure that shipping on the Great Lakes is not affected.

Under the proposed rules, off-shore facilities will also be subjected to a “stringent and comprehensive application process,” including meeting requirements that minimize negative impacts to threatened species and their habitat, assessing and addressing any potential negative environmental effects, noise assessments and public consultation requirements, among other things.

These draft rules have been released in the middle of the Ministry of Natural Resources review of Ontario’s Crown land release process applicable to renewable energy projects. Begun in September 2009, the first phase focused on procedural elements, like ensuring clarity between site release and other provincial approval processes, while the second phase focuses on longer-term policy direction for renewable energy developments on Crown land. Results from the first phase are now available for comment on the Environmental Registry and results from the second phase are expected in 2010.

OPA Issues hundreds of FIT Contracts

Alison Forbes

Although many kinks and details in the Ontario Power Authority (OPA) Feed-in-Tariff (FIT) program continue to be ironed out, more than six hundred developers of renewable energy generation facilities have been awarded FIT contracts since early March, representing approximately 2600 MW in generation capacity. The impressive uptake of the program seems to have come as a surprise to both the OPA and the provincial government, although the economics of developing renewable-energy generation projects under the FIT program was no secret among developers.

Capacity allocation exempt facilities

The OPA announced the first tranche of FIT contracts on March 10 - more than five hundred FIT contracts were offered to developers of projects with a generation capacity of less than 500 kWs. These "Capacity Allocation Exempt" (CAE) facilities represent a total of 112 MWs of generation capacity and are largely comprised of rooftop solar projects. CAE facilities are not required to provide initial application security upon the submission of an application under the FIT program, and are exempt from the OPA's distribution and transmission capacity testing. Although the OPA had originally intended to offer contracts to CAE project applications immediately after applications had been deemed complete, no further CAE facility FIT contracts will be offered until June, at the earliest.

Large-scale facilities

The OPA announced the second tranche of FIT contracts on April 8 - more than 180 FIT contracts representing almost 2500 MW of generation capacity. This is the first time that large-scale renewable energy projects have been able to access a standard offer contract program offered by the OPA. The Renewable Energy Standard Offer Program (RESOP) was replaced by the FIT program, but was limited to projects of 10 MW or less. Projects offered contracts under FIT range in size from less than 1 MW to 300 MW. Although seventy-six contracts were offered to proposed solar projects (representing 651 MW), the majority of the proposed generation capacity comes from on-shore wind projects, with forty-seven contracts offered to projects totaling more than 1229 MWs of capacity. One FIT contract was offered to a proposed offshore wind project with a proposed capacity of 300 MW. Once the contracts are finalized, project developers have a limited time to bring these projects online - three years from the date of contract for solar and wind projects.

Renewable energy - truly a sustainable resource?

The unprecedented growth of the renewable-energy generation market in Ontario over the first six months of the FIT program has many people questioning whether this rate of growth can be sustained. More than 2600 MW of capacity has been contracted for under FIT, which is double the 1300 MWs of renewable generation that has been developed in Ontario since 2003.

Generation is only one component to the growth of the electricity market in Ontario. Transmission and manufacturing are two other critical keys to ensuring these six-hundred-plus projects can be brought on to the Ontario grid. The FIT contracts granted so far have been assessed in light of the province's current transmission and distribution capacity, and will not require substantial expansion of either grid. But there remain more than 250 projects waiting for the OPA's "Economic Connection Test" (ECT), having been deemed by the OPA not economically viable under current transmission and distribution capacities. The ECT is intended to reassess the viability of proposed projects as new transmission capacity comes online. The completion of the approval process of the Hydro One Networks Inc. (HONI) Bruce-Milton transmission project represents a significant expansion of HONI's transmission grid and will add 1500 MW of transmission capacity to that region. The OPA has planned to run the first ECT in early fall 2010 and expects the Bruce-Milton transmission line will result in new FIT contracts being issued to projects affected by this development. The critical question that remains is "what next?" - HONI has been issued a directive from the provincial government to significantly build out its transmission capacity, and while the OPA and HONI have indicated that work on this expansion has begun, the timeline for the completion of any new transmission work is not clear, even for the Bruce-Milton line. Historically, obtaining all necessary approvals for transmission development projects can take years, and components of the Green Energy Act intended to streamline this process have yet to be tested.

The projects offered FIT contracts so far may not have to worry about transmission but, for the wind and solar projects, the domestic-content rules under the FIT contract continue to represent a significant hurdle to bringing these projects online. Currently, solar projects must meet a 50% domestic-content threshold and wind projects must meet a 25% domestic-content threshold; in 2011 the solar requirement is increased to 60% and in 2012 the wind requirement is increased to 50%. The 2011 and 2012 deadlines have caused many developers to fast-track development and construction plans for facilities granted FIT contracts in order to avoid the significantly more difficult domestic-content obligations. The OPA has been working with FIT program participants to try to clarify developer obligations under this aspect of the FIT contract. In March, the OPA announced that it will review and provide comments on a project's domestic content plan before the "Notice to Proceed" date, a change that will allow developers to get the OPA's feedback on certain equipment prior to entering into supply agreements. Further, the OPA has also indicated that it will provide developers with a non-binding reliance letter confirming that a project will meet the applicable domestic-content obligations under the FIT program. This is aimed at minimizing the significant barrier to financing FIT program projects that many project developers have been facing. Even with the changes to the domestic-content obligations thus far, many developers are hoping that the 2011 and 2012 deadlines will be extended.

The FIT program remains open to new applications; the OPA has received almost one thousand applications to date and more are expected. The announcement of the issuance of FIT contracts is an important step towards realizing the provincial government's goals under the Green Energy Act, but it is just that - a step. There remains considerable work to be done by developers, the OPA, local distribution companies, HONI, and the provincial government before any of the announced 2600 MW of renewable generation capacity starts powering the homes of Ontarians.

Renewable power continues to energize project development in Ontario

Alison Forbes and Jim Harbell

As the dust finally settles from the 60-day initial launch period in the Fall of 2009 under the Ontario Power Authority (OPA) Feed-in Tariff (FIT) program, many project developers, renewable energy generation equipment manufacturers, investors, lenders and governmental agencies are quickly realizing that Ontario's renewable energy market is experiencing explosive growth. This article briefly reviews some of the most recent developments.

FIT program - launch period closes

On December 16, 2009, the OPA announced that more than 1200 microFIT applications (10 kW or less) and more than 1000 FIT applications were received throughout last October and November, representing nearly 9000 MW of potential electricity generation. Rooftop solar projects amounted to more than 97% of the microFIT applications. The OPA has already sent out more than 700 offers to enter into microFIT contracts for those applications received during the launch period and intends to start offering conditional contracts to those applications received after the launch period in February 2010. Project applications under the FIT program were divided between wind (79%), solar (16%) and biofuels and water (5%).

Although the OPA has estimated that there is approximately 2500 MW of available transmission capacity, the overwhelming popularity of the FIT program based on the submission of FIT applications to date and the announcement of the Samsung deal had left many potential developers wondering what progress has been made to develop new transmission capacity and when will that capacity be operable. The Distribution Availability (DAT) and Transmission Availability Tests (TAT), as well as the Economic Connection Test (ECT), all components of the application assessment under the FIT Program, will be critical tools to ensuring that the most shovel-ready projects can proceed as quickly as possible. The OPA has recently announced that it expects to start issuing contract offers to project launch applications in the next few weeks. Those projects not issued contracts will be subject to the ECT, which will be run on a regional basis and is tentatively scheduled to commence as early as the spring of 2010. It should be noted that DATs and TATs will be paused for periods of three months during the operation of an ECT in the applicable region - which will slow down the application review process. The OPA continues to accept FIT and microFIT applications and with the first ECT occurring imminently, prospective developers are working to ensure that new applications are received before the deadline for ECT consideration, being sixty days before the test begins.

Ministry of Natural Resources - Crown land release process

While project developers anxiously await news of FIT contract offers, the Ministry of Natural Resources (MNR) has released proposed revisions to its Crown land release process for windpower projects and the MNR and the Ministry of Environment (MOE) have each recently issued guides to the new permitting and approval framework for renewable energy projects in Ontario.

The MNR released draft revisions to its Windpower Site Release - Crown Land Policy and Procedure in late December, which outline the distinct stages in the process of developing windpower projects on Crown land including off-shore wind projects. Following the moratorium on Crown land applications for windpower projects in place since September 24, 2009, these proposed amendments represent the first phase of the MNR's review of its Crown land release process, and are intended to address the concerns of project developers with current applications under review by the MNR. The second phase of this review will focus on the long-term application of the site release process and the policy direction for renewable energy developments on Crown land in the context of Ontario's new green energy initiatives. It is unclear how the second phase of the review will affect developers who have not yet submitted applications under the site release process or when the MNR's review of this process will be completed.

The proposed revisions provide that the MNR will periodically establish "windows of opportunities" during which project developers may apply for the opportunity to secure Crown land. It is unclear how often and for what duration such "windows of opportunities" will be opened. The MNR must complete its initial review of an application for Crown land and schedule a pre-screening meeting with the applicant within 60 days after the receipt of the application. Following a required consultation process, the MNR will either issue an Applicant of Record (AoR) letter or deny the application. No estimate has been provided on how long the consultation process will take. Once an AoR letter has been issued, the formal site release process is complete. The MNR has expressly clarified that neither an application for Crown land nor an AoR status provides any right, title or interest in land and only the AoR status is transferable in limited circumstances. Following receipt of necessary approvals related to the proposed project, the MNR will instruct the applicant to submit an application for Crown land, which will include a current corporate profile and specified survey requirements. Authorization to construct the proposed project will be by Crown Lease, the term of which is generally 25 years. In certain instances, an interim Land Use Permit may be issued until all survey requirements are met (for a maximum period of one year).

Approval and permitting requirements for renewable energy projects

The MOE released its guide to the Renewable Energy Approval (REA) in late January, clarifying the new approval process that most renewable energy projects must undergo (there are limited exemptions for small-scale projects). The MOE, as the ministry responsible for coordinating the necessary review of proposed projects, has undertaken to complete the REA process within six months of receipt of a complete submission. Among the things that are to be included in submission packages are:

 

  • a project description report
     
  • a construction plan report
     
  • a consultation report
     
  • a design and operations report
     
  • a decommissioning plan report
     
  • technical reports
     
  • proof that setback requirements are met, and
     
  • archaeological and heritage resource studies/reports.

The REA regulations require that a project developer commence consultation with the applicable municipality, Aboriginal groups, and the public at least 90 days before submitting a REA application. Further, a developer must coordinate with the MNR in respect of certain issues falling under the MNR's scope of review, including those related to the Endangered Species Act and the Fish and Wildlife Conservation Act, in advance of a developer's REA application submission. As this new approval process has just begun, it remains unclear how long the entire process will take. This is particularly so given the need to file a complete application. Fulfilling the application requirements may be onerous and time-consuming, which may lead to uncertainty. Further, coordination with the federal environmental assessment process and the MNR release of Crown land process remains unclear.

Clarifications and updates to the OPA FIT Program

Alison Forbes

Since its release of the Feed-In Tariff (FIT) program on September 30, 2009, the Ontario Power Authority (OPA) has faced both commendation and criticism. Throughout the Launch Period, ending November 30, 2009, the OPA has released several clarifications and amendments to the initial FIT program. The following is a summary of the key announcements made throughout the past two months and some of the issues that remain outstanding.

Key Recent Announcements

Domestic Content Technical Notes: This component of the FIT program has raised extensive criticism from proponents. The OPA has indicated that the requirements set out in the original FIT contract will not be changed but has now provided further technical notes to assist proponents in interpreting these obligations. These notes can be found on the OPA website and will be updated periodically.

Agricultural Land Restrictions for Solar PV: The OPA has announced that it will provide guidelines for proponents that detail the benefits of more renewable energy with the need to protect Ontario's prime agricultural land and details on exemptions available for lands zoned for non-agricultural purposes. Contained within these guidelines will be details on the evidence that a proponent must provide for proposed projects on such lands. These guidelines have not been released as of the date of this update.

Transition options for microFIT (< 500 kW) projects: On October 30, 2009, the OPA announced new options for microFIT proponents that have projects in the late phases of development. These new options exempt such projects from domestic content requirements. Eligible proponents must have either a previous RESOP contract or have purchased generation equipment prior to October 1, 2009 and may elect to transition into the microFIT program or amend the RESOP contract to reflect microFIT prices.

Critical questions

Priority Access: As many generators are aware, Ontarian's demand for electricity has been, at certain times, well below the available generated load on the system. Renewable energy projects have been given a priority right of access to connect to the grid under amendments arising from the Green Energy Act (GEA) but have no defined prioritized right in the actual sale of generated electricity into the grid. As curtailment decisions from the Independent Electricity System Operator (IESO) and Local Distribution Companies (LDCs) become more common, renewable energy generators face the same risk of generation limitation that all other generators, including large scale gas generators, face.

Transmission and Distribution: The popularity of both the old Renewable Energy Standard Offer Program (RESOP) and the FIT program clearly indicates that there are countless project developers interested in entering the generation market. The current determining factor of how quickly these proponents are able to begin selling electricity is transmission and distribution capacity. Hydro One Networks Inc. (HONI) has been directed by the government to commence a large-scale transmission expansion program which is planned to be on stream between 2013 and 2017. Many proponents have raised concerns that the required expansions in both the transmission and distribution systems will cause significant delays in meeting the demand of proposed renewable energy generation facilities.

Conservation and Demand Management (CDM) and Smart Grids: Conservation was a key component to the GEA and it is expected that LDCs will play an important role in the development of CDM protocols. It is anticipated that CDM targets will be made a condition of distribution licences but the details of such an amendment have not been released. The Ontario Energy Board is expected to develop a CDM Code in the coming weeks which will provide a framework on licensing targets and CDM programs.

Despite the concerns raised by many renewable energy project proponents, the FIT program has been, thus far, very well received. As of November 10, 2009, the OPA had received more than 90 applications under the FIT program, representing more than 78 MW of generated capacity and nearly 500 applications under the microFIT program, representing more than 2.5 MW of generated capacity. In comparison to the RESOP program, which contracted more than 1,316 MW of renewable generation, these numbers seem small but the OPA has indicated that it expects these will more than double before the end of the Launch Period. After the November 30, 2009 deadline, the FIT program remains open to applications, although the standard contract rules for time stamping and transmission/distribution capacity allocation become applicable.

OPA's FIT program kicks off and REA regulations come into force

Jim Harbell and Alison Forbes

As Ontarians turned off their air conditioners earlier this month, the Ontario Power Authority (OPA) opened the gates to the widely anticipated Feed-In-Tariff (FIT) Standard Offer Contract Program. The FIT program was officially launched on October 1, 2009, finally allowing renewable-energy project developers to put the FIT framework to the test. The OPA has stated it intends to respond to project developers within sixty days of receiving a complete application, although the anticipated high number of applicants may cause delays to the expected execution of FIT contracts.

Key features of the FIT program

  • Generally, in order to be eligible, projects must be (a) renewable generating facilities not already in existence; (b) located in Ontario, provided they are not located in expressly exempt areas; and (c) projects that do not have or have not had a prior power purchase agreement, unless such agreement was terminated prior to March 14, 2009 or more than twelve months before the date of application.
     
  • Solar projects with a contract capacity greater than 100 kW are not eligible if located on certain high-quality Class 1 or Class 2 agricultural lands, and, if located on Class 3 agricultural lands, are only eligible if located on identified lands.

Application

  • Application fees under the FIT program range from a minimum of $500 to a maximum of $5000, and the application security charge is $20/kW for solar projects and $10/kW for all other projects.
     
  • A complete application must also include evidence of access rights to the project location. Such evidence may be in the form of a lease, an option, a letter of intent, a memorandum of understanding or a conditional grant contingent on obtaining a FIT contract.

Domestic Content

  • The domestic content of a project is calculated based on the OPA's domestic content grid for each specified renewable energy source and contract capacity. This grid allocates a qualifying percentage to designated activities occurring within Ontario or completed by Ontario residents. Designated activities include the manufacturing and assembling of specified materials, certain construction and on-site labour, and certain consulting services.
     
  • The following domestic content thresholds must be met:
     
    • wind power projects with a contract capacity greater than 10kW: (a) 25% for FIT contracts with a milestone commercial operation date (COD) prior to January 1, 2012; and (b) 50% for FIT contracts with a milestone COD on or after January 1, 2012;
       
    • solar projects with a contract capacity greater than 10 kW: (a) 50% for FIT contracts with a milestone COD prior to January 1, 2011; and (b) 60% for FIT contracts with a milestone COD on or after January 1, 2011;
       
    • solar projects with a contract capacity less than 10 kW: (a) 40% for FIT contracts with a COD prior to January 1, 2011; and (b) 60% for FIT contracts with a COD on or after January 1, 2011;
       
  • The OPA must be provided with a plan, in a prescribed form, setting out how the FIT program applicant intends to meet the minimum required domestic content level, no later than six months prior to the milestone COD.

Launch Applicants

  • All eligible FIT contract applicants who apply during the first sixty days following the launch of the FIT program (prior to November 31, 2009) will be assigned a time stamp, allocated in priority based on (a) the applicant's commitment to reduce the number of days between the date of contract and the milestone COD; (b) the project's acceleration characteristics, including whether it is REA exempt or has an executed EPC agreement; and (c) the date access rights were granted.

Advanced RESOP Applicants

  • A Project Developer with a Renewable Energy Standard Offer Program (RESOP) contract can either: (a) retain the RESOP, unamended; (b) amend the RESOP before October 31, 2009, through the FIT program's Advanced RESOP FIT Amendment, where the RESOP is in respect to a wind generation project that has been issued a Certificate of Approval (Noise Emissions) from the Ministry of Environment; (c) repudiate and terminate the RESOP by applying through the FIT Program Launch, before November 31, 2009; or (d) repudiate and terminate the RESOP and apply through the standard FIT program after twelve months.
     
  • The Advanced RESOP FIT Amendments include:

    • a substitution of the contract price with 12.1¢/kWh, comprised of a fixed portion of 9.68¢/kWh and an indexed portion of 2.42¢/kWh;
       
    • relief from the requirements of the RESOP to share with the OPA payments the applicant may be able to obtain under the ecoENERGY grant;
       
    • a requirement to maintain the completion and performance security, which will be returned on the COD; and
       
    • a requirement that the facility achieve commercial operation no later than December 31, 2010, with liquidated damages payable for each day commercial operation is late, culminating in an event of default if the COD is after December 31, 2011.
  • Project developers who amend their RESOPs remain bound by the RESOP contract and are not subject to the terms of the FIT program, including domestic content requirements.

MicroFIT

  • microFIT is a standard-offer program focused on homeowners and other micro-project developers. The rules and the governing contract have been simplified, but contain similar obligations regarding domestic content and environmental attributes. There are no application or security fees associated with contract application under the microFIT rules.

Renewable Energy Approvals

In addition to the commencement of the FIT program, the Ministry of the Environment released key regulations on September 24, 2009 relating to the Renewable Energy Approval (REA) amendment under the Environmental Protection Act.

A REA is required for all projects which were previously required to seek certificates of approval under s. 9(1) and (7) of the EPA (i.e. construction, altering, extending or replacing or operating any plant, structure, equipment, apparatus, mechanism or thing that may discharge or from which may be discharged a contaminant into any part of the natural environment other than water), s. 27(1) (waste management), and all those that generally were required by regulation to seek an "approval, permit or other instrument."

Prior to the EPA REA amendments, solar projects were not required to undergo an environment assessment (EA). Wind projects may have had to undergo an environmental impact study or potentially a full EA, depending on the location and the project's generation capacity. Certificates of Approval were required by regulation for both wind and solar projects.Projects are exempt from seeking a REA where:

 

  • all approvals, permits and other instruments that are required to construct, install, operate or use the facility were obtained before May 14, 2009;
     
  • no approvals, permits or other instruments listed above were required to construct, install, operate or use the facility and the construction or installation of the facility began before May 14, 2009;
     
  • an EA Notice of Completion in respect of the facility was issued prior to May 14, 2009 and the facility has a power purchase agreement with the OPA;
     
  • before May 14, 2009, (i) a power purchase agreement was entered into with the OPA; (ii) the use of the land at the project location was not prohibited by a zoning by-law or order under Part V of the Planning Act; and (iii) the facility was not an undertaking that was designated to be subject to the Environmental Assessment Act.

General REA obligations include:

 

  • consultation with the public and aboriginal communities surrounding the project, including at least two public meetings;
     
  • consideration of archaeological and heritage resources, where applicable;
     
  • specified setbacks for wind energy facilities;
     
  • submission of a project's construction plan report, construction report, decommission plan report, design and operations report, noise study report (for non-rooftop solar facilities with a capacity greater than 10 kW), project description report, and wind turbine specifications report or off-shore wind facility report (where applicable).

Care should be taken when reviewing the various transition provisions related to the RESOP and FIT programs and the REA requirements.

Commentary

The Ontario government should be pleased with the level of activity in the renewable sector these days. There is a flurry of new entrants, particularly from the U.S. and Europe, who are thoroughly investigating opportunities in Ontario, from both development and equity investment perspectives. At the same time, some organizations are suggesting that the FIT program needs to be more user friendly. For example, the solar industry is concerned about the restriction on the use of Class 1, 2 and 3 agricultural lands and is looking for certain relief from those provisions , as well as some loosening of the domestic content requirements. Those same domestic content requirements, which while lower for wind applicants, are also being raised as concerns by the wind industry. Both solar and wind proponents note that the current capacity in Ontario for meeting the domestic content requirements is seriously constrained and more time than the government has allowed may be necessary to meet the deadlines imposed. Finally, the great unknown-issues relating to transmission capacity constraints-will start to reveal themselves in the months to come, once the initial round of FIT applications are reviewed and queues start to form for new transmission development. Stay tuned for further word from the OPA as they work through the first round of mature applications that will be filed prior to the end of November 2009.

The launch of the FIT program and the commencement of the REA represent the final pieces that complete the implementation of Bill 150, which was first introduced in February. Watch for further guidance from both the OPA and the Ministry of Environment as these new pieces are "fit" into place.

We will continue to keep you regularly informed as the FIT marketplace develops and matures.

OPA releases new FIT Program rules

Annie Pyke

On July 10, 2009, the Ontario Power Authority (OPA) released updated rules (Program Rules) for the Feed-In Tariff Program (FIT Program). The purpose of the FIT Program is to promote the development of renewable energy sources within the province of Ontario through the creation of a standardized application and approval process for renewable electric generation. The FIT Program is an important element of the Green Energy and Green Economy Act (GEA). The following briefly highlights the basic FIT structure and significant revisions to the Program Rules.

The basic eligibility requirements for the FIT Program are that the facility must: (i) be a new or incremental generating facility; (ii) be located in Ontario; and (iii) generate electricity from one or more of: wind, solar (photovoltaic), landfill gas, waterpower, biogas, or renewable biomass. A new requirement is that applicants must also provide evidence of the necessary title and access rights to construct the project (the "Access Rights," as defined in the Program Rules), which is more detailed than the previous requirement of "Demonstrated Location Access." The Program Rules also move the requirement that applicants give evidence of resource assessment/planning and Renewable Energy Approval from the application stage to the FIT Contract stage.

Although the requirement is not a condition for application to the FIT Program, it is important to note that certain projects will be required to achieve a certain level of "Provincial Content," pursuant to the FIT Contract. The definition of "Provincial Content" is still under review; however, other sections of the Program Rules make reference to an "irreversible manufacturing process" that occurs in Ontario.

The Program Rules also set out specific rules for Community Participation Projects and Aboriginal Participation Projects. Community and Aboriginal Participation will be assessed based on the aboriginal or community proponent's economic interest in the project. A project that receives either of these designations receives, among other benefits, reduced security requirements and an increased price/MW.

One of the most significant changes to the Program Rules is the inclusion of rules that specifically apply to early applications - i.e., Program Launch (a time period to be defined by the OPA).  These rules include "rated criteria," whereby applicants receive points for non-mandatory attributes.  The new rated criteria indicate the OPA's focus on ensuring that the initial projects awarded FIT Contracts will be able to begin construction immediately and achieve commercial operation on an expedited basis, to assist the Government of Ontario in achieving the goals of the GEA.

Ontario MoE releases proposed minimum setback requirements for wind energy

On June 9, 2009, the Ontario Ministry of the Environment released the "Proposed Content for the Renewable Energy Approval Regulation under the Environmental Protection Act" (the Proposal). The intent of the Proposal is to standardize requirements applicable to developers of renewable energy projects across the province. One such proposed requirement would oblige developers to locate renewable energy projects at a minimum setback distance from "receptors", such as dwellings, to ensure that noise levels do not exceed a certain threshold at any receptor.

Although setbacks requirements would apply to wind, solar, hydro, biogas, and biomass projects, the standardization of setback distances is specifically intended to target wind projects. At present wind developers are subject to multiple setback distance requirements as dictated by municipal governments. The Proposal would require that wind projects are set back a minimum of 550 metres from any receptor. A higher standard would be imposed depending on factors such as: (1) the number of turbines in the proposed development; (2) any existing or approved turbines in the area; and (3) the sound level rating of the turbines selected for the development. The Proposal also provides for a minimum setback from roads, railways, and side and rear lot lines that is equal to the turbine hub height plus the length of the blade.

In addition to recommending minimum setback distances, the Proposal would require noise studies to be conducted for any project involving wind turbines with a sound power level greater than 107 decibels, regardless of number, and for any project involving more than 26 turbines within 1.5 kilometres of any receptor. These studies would form part of the new provincial approval process for renewable energy projects.

The Proposal is open for public review and comment on the Environmental Registry until July 24, 2009.

NIMBYism, low frequency noise and wind energy development

Aaron Atcheson

The movement known as NIMBY(Not In My Backyard)-ism is taking its toll on Canadian renewable energy projects, particularly on wind farm developments. The latest of the bogeymen used to stop or slow down these projects is the spectre of serious health effects arising from low frequency noise produced by turbines.

NIMBYism is certainly not a new phenomenon, but rather has been a consistent theme within environmental movements since their inception. To a certain extent, renewable energy projects have been supported by the larger environmental movement, keeping NIMBYism at bay. However, unresolved questions about the potential health effects of low frequency noise (LFN) associated with modern wind turbines have become the latest fodder for the NIMBY movement.

LFN, which is generally described as noise in the frequency range of 10 Hz to 200 Hz, has been linked by media reports to sleep disturbance, fatigue, migraine headaches and depression. LFN emissions were characteristics of some early wind turbine models, particularly where turbine blades were downwind of the main tower. With modern wind turbine designs, which have their blades upwind of the tower, the "wind shade" behind the tower is avoided, and LFN is significantly reduced.

Experts agree that LFN, at sufficient levels, may be a health concern for those who are sensitive to its effects. The effects of inaudible levels of LFN have not been sufficiently studied to date to rule out the possibility of health effects, but commentators have weighed in on each side of the debate. Setbacks and noise surveys are common requirements imposed on new wind farm developments, in part to minimize the risk of wind turbines causing health effects on local residents.

Media reports have recently focussed on claims of adverse health impacts from LFN. Earlier this year, a family from Lower West Pubnico, Nova Scotia abandoned their home, located approximately four hundred metres from the nearest turbine. Daniel d'Entremont and his family complained of lack of sleep, fatigue, headaches and a lack of concentration. And while the d'Entremont family may have legitimate concerns about the particular wind farm they claim was affecting their lives (new sound testing has been commissioned by the federal government), such reports are being used by those opposed to wind farm development to slow down or stop projects.

Several significant Canadian projects have been abandoned in recent months because of public pressure. Brookfield Power abandoned a proposal to build a thirty-turbine farm in the Blue Mountain area because of delays in receiving permits, and Enbridge has cancelled plans to install eleven turbines in the community of Saugeen Shores because of a local requirement for a 250 metre setback. Other projects that have been slow to receive approvals are encountering local criticism based on potential LFN effects.

Ontario Energy Minister Dwight Duncan was recently quoted as saying that some people have moved past NIMBY to NOPE (Not On Planet Earth) or BANANA (Build Absolutely Nothing Anywhere), and that these phenomena are a threat to the province's energy security. It appears that NIMBYism will be with the wind energy industry for some time to come; only a combination of more information and strong political direction will allow the industry to reach its full potential.